Phase 2 Modernization

Dwyer Middle School

Project Overview

Dwyer Middle School has transformed dramatically under the Measure Q Bond Program. Phase 1 modernization work included significant improvements to the classrooms and administrative facilities. Classrooms campus-wide have been upgraded with the latest 21st Century technology and furniture.

Phase 2 projects renovated the more modern Case Building, which includes math and science classrooms and labs, as well as a new mural to refresh the exterior of the original school facility. The library was converted to learning commons, and the food services spaces were activated into a social environment where students can socialize, engage and collaborate. The new student hub is a place to see and be seen!

SERIES

B

MASTER PLAN CONSTRUCTION BUDGET

$7,918,900

ACTUAL CONSTRUCTION COST

$5,584,752

CONSTRUCTION CONTINGENCY RETURNED

$274,134

MASTER PLANNED COMPLETION DATE

November 2019

ACTUAL COMPLETION DATE

November 2020

CONSTRUCTION DURATION

17 months