Phase 2 Modernization
Dwyer Middle School
Dwyer Middle School has transformed dramatically under the Measure Q Bond Program. Phase 1 modernization work included marked improvements to the classrooms and administrative facilities. Classrooms campus-wide have been upgraded with the latest 21st Century technology and furniture.
Phase 2 projects renovated the more modern Case Building, which includes math and science classrooms and labs, as well as a new mural to refresh the exterior of the original school facility. The library was converted to learning commons, and the food services spaces were activated into a social environment where students can socialize, engage and collaborate. The new student hub is a place to see and be seen!
SERIES
B
MASTER PLAN CONSTRUCTION BUDGET
$7,918,900
ACTUAL CONSTRUCTION COST
TBD *
* Project is currently under construction
CONSTRUCTION CONTINGENCY RETURNED
N/A
MASTER PLANNED COMPLETION DATE
November 2019
ACTUAL COMPLETION DATE
TBD *
* Project is currently under construction; estimated completion November 2020