Phase 1 Modernization

Hawes Elementary School

Project Overview

The primary focus of the renovation at Dr. Ralph E. Hawes Elementary School was to implement a 21st Century learning environment in an overall effort to upgrade the classrooms district-wide to next generation learning standards. Hawes Elementary School also received health, code and safety improvements, such as those mandated by AB 300, accessibility and other systems/infrastructure updates.

The 21st Century classroom renovations provided new furniture and interactive technology to improve the learning environments and allow maximum flexibility in how instructional material is taught and presented. Specific furniture and technology were selected for each classroom space that appropriately caters to each grade level.

SERIES

A

MASTER PLAN CONSTRUCTION BUDGET

$9,266,400

ACTUAL CONSTRUCTION COST

$6,136,305

CONSTRUCTION CONTINGENCY RETURNED

$268,546

MASTER PLANNED COMPLETION DATE

October 2018

ACTUAL COMPLETION DATE

August 2019

CONSTRUCTION DURATION

11 months