21st Century Demonstration Classrooms

Moffett Elementary School

Project Overview

Huntington Beach City School District is committed to being a model for 21st Century education. As such, classrooms were transformed across the District into innovative student-centered spaces that support collaboration and flexibility.

Classroom 16 (5th Grade) and one general classroom were designated at S. A. Moffett Elementary School to be renovated and serve as learning labs. OnPoint Innovative Learning Environments and Studio W Architects engaged the demonstration classroom teachers to guide them through the design and functional concepts that were integrated into their spaces. Upon completion in Fall 2017, OnPoint administered professional development related to the new technology and equipment that was installed to support and administer curriculum.

The demonstration classrooms were used to elicit and gather feedback from the educators, which served as the framework to transform all the classrooms across the District into innovative 21st Century learning environments.

SERIES

A

MASTER PLANNED CONSTRUCTION BUDGET

$93,500 *

ACTUAL CONSTRUCTION COST

$192,244 *

CONSTRUCTION CONTINGENCY RETURNED

N/A

* The Facilities Master Plan included one demonstration classroom. However, two demonstration classrooms were constructed.

MASTER PLANNED COMPLETION DATE

Fall 2017

ACTUAL COMPLETION DATE

Fall 2017

CONSTRUCTION DURATION

2 months