Phase 1 Modernization
Dwyer Middle School
Project Overview
The main classroom building at Ethel R. Dwyer Middle School was completely renovated, including upgrades to all classroom spaces to transform them into 21st Century learning environments. The rooms are equipped with agile, movable furniture and interactive technology to allow maximum flexibility in how instructional material is taught and presented. Each space was outfitted with specific furniture and technology customized to the particular program of that classroom. Improvements were also made to the administration lobby.
SERIES
B
MASTER PLANNED CONSTRUCTION BUDGET
$5,974,378
ACTUAL CONSTRUCTION COST
$5,952,380
CONSTRUCTION CONTINGENCY RETURNED
$529,000
MASTER PLANNED COMPLETION DATE
October 2018
ACTUAL COMPLETION DATE
October 2018
CONSTRUCTION DURATION
4 months
[rrj_bar_chart title=”Construction Budget” orientation=”horz” labels=”Original;Actual” stack_mode=”bars” datasets=”%5B%7B%22tooltips_format%22%3A%22%7Bd%7D%3A%20%7By%7D%22%2C%22values%22%3A%2210%3B%208%3B%2011%22%2C%22color%22%3A%22%233953a4%22%2C%22bar_bg%22%3A%22plain%22%7D%5D” legend=”” legend_onclick=”” tooltip=”” ar=”21:9″ axes_color=”rgba(89,89,89,0.8)” axis_prefix=”$” axis_suffix=”M”]