Phase 2 Modernization

Smith Elementary School

Project Overview

The modernization of Agnes L. Smith Elementary School was completed in two parts and included campus-wide classroom renovations and a new administration and classroom building. Part I was completed in August of 2020 and consisted of transforming the classrooms to align with the District’s goal of renovating all facilities to support the latest technology, equipment, furnishings and teaching methodologies of next generation learning.

Part II was completed January 2021 and includes a new classroom and administration wing. This new building shifts the entry of the school to 17th Street while providing enhanced site safety and security. After administrative staff move into the new facility, the former administration space and learning resource center will be modernized along with improvements to the multi-purpose and food service facilities.

SERIES

B

MASTER PLANNED CONSTRUCTION BUDGET

$15,352,700

ACTUAL CONSTRUCTION COST

$17,247,399

CONSTRUCTION CONTINGENCY RETURNED

$659,140

MASTER PLANNED COMPLETION DATE

August 2020

ACTUAL COMPLETION DATE

January 2021

CONSTRUCTION DURATION

19 months