Phase 1 Modernization

Dwyer Middle School

Project Overview

The main classroom building at Ethel R. Dwyer Middle School was completely renovated, including upgrades to all classroom spaces to transform them into 21st Century learning environments. The rooms are equipped with agile, movable furniture and interactive technology to allow maximum flexibility in how instructional material is taught and presented. Each space was outfitted with specific furniture and technology customized to the particular program of that classroom. Improvements were also made to the administration lobby.

 

SERIES

A

MASTER PLANNED CONSTRUCTION BUDGET

$7,973,080

ACTUAL CONSTRUCTION COST

$4,778,262

CONSTRUCTION CONTINGENCY RETURNED

$529,000

MASTER PLANNED COMPLETION DATE

October 2018

ACTUAL COMPLETION DATE

October 2018

CONSTRUCTION DURATION

4 months