Phase 3 Modernization

Eader Elementary School

Project Overview

The modernization of John H. Eader Elementary School was comprised of 21st Century improvements to all classrooms, including the replacement of window systems and electrical infrastructure. The library was improved to become a modern learning commons, along with new restroom facilities. Additional site improvements include upgrades to the accessible parking and roofing systems, as well as health, code, safety and accessibility updates.

SERIES

C

MASTER PLANNED CONSTRUCTION BUDGET

$6,701,200

ACTUAL CONSTRUCTION COST

$10,123,771

CONSTRUCTION CONTINGENCY RETURNED

$131,939

MASTER PLANNED COMPLETION DATE

October 2022

ACTUAL COMPLETION DATE

August 2022

CONSTRUCTION DURATION

14 months