Project Overview

Huntington Beach City School District is committed to being a model for 21st Century education. As such, classrooms were transformed across the District into innovative student-centered spaces that support collaboration and flexibility.

Classroom 21 (5th Grade) was designated at Huntington Seacliff Elementary School to be renovated and serve as a learning lab. OnPoint Innovative Learning Environments and Studio W Architects engaged each of the demonstration classroom teachers to guide them through the design and functional concepts that were integrated into their space. Upon completion in Fall 2017, OnPoint administered professional development related to the new technology and equipment that were installed to support and administer curriculum.

The demonstration classrooms were used to elicit and gather feedback from the educators, which served as the framework to transform all the classrooms across the District into innovative 21st Century learning environments.

SERIES

A

MASTER PLANNED CONSTRUCTION BUDGET

$93,500

ACTUAL CONSTRUCTION COST

$120,183

CONSTRUCTION CONTINGENCY RETURNED

N/A

MASTER PLANNED COMPLETION DATE

Fall 2017

ACTUAL COMPLETION DATE

Fall 2017

CONSTRUCTION DURATION

2 months