Phase 2 Modernization

Seacliff Elementary School

Project Overview

The renovation of Huntington Seacliff Elementary School entailed a campus-wide modernization of classroom spaces into modern and globally competitive learning environments. This included the library, which was converted into a state-of-the-art learning commons with collaboration spaces in the corridors to further enhance the philosophy that “learning happens everywhere.” The administration area was renovated to improve the functionality and flow of the interior spaces.

The school was outfitted with new, adaptable furniture that can be moved and reconfigured to support a variety of different teaching and learning methodologies. New technology, health, code and safety improvements, site upgrades, parking/drop-off improvements, and infrastructure and systems replacements round out the scope of the modernization project.

SERIES

B

MASTER PLANNED CONSTRUCTION BUDGET

$5,199,700

ACTUAL CONSTRUCTION COST

$7,019,815

CONSTRUCTION CONTINGENCY RETURNED

$680,795

MASTER PLANNED COMPLETION DATE

August 2021

ACTUAL COMPLETION DATE

November 2021

CONSTRUCTION DURATION

20 months